THE
COMPONENTS.
- D.U.
Kit ® rail includes P.V.C Liner 4
meters. in length, or as per your individual requirements.
- 4 pc of bases per unit (
threaded rod length according to the concrete thickness) or as per your
individual requirements.
- 8pc adjustment nuts +8pc
retaining springs( two for each base)
INSTRUCTIONS
- Mark the lines where
the D.U.
Kit® should be
placed
- Place the bases under the
string, to the desired intervals.
- Install the adjustment nuts on
the threaded rods to the approximate height( with the hexagonal part
facing downwards)
- Place the D.U. Kit ® on top of the nuts. ( The nuts should fit into the
smaller (16mm). holes)
- Insert the retaining springs
into the grooves in the upper sides of the nuts.
- Adjust the placement of
the D.U. Kit
®
rails according to the where
the string is placed.
- Fasten the bases to the
substrate with the pegs placed in the holes. ( In the case of concrete
substrate, use HILTI or similar bolts)
- Adjust the D.U. Kit ® to the desired height,
using the special key supplied. ( It is recommended to turn both nuts,
on each base, concurrently)
- When all the above elements
are set- it is possible to proceed with the casting!
|

|