THE COMPONENTS
- Omega rail with P.V.C.
liner, 4 meters in length, or according to the client's specifications.
- 4 pc. of bases per each
standard rail, or according to the customer''s specifications.
- 4 pc. of bolts M-6+4 pc
of nuts, on a ratio of one per base.
- 8-10 pc. of peg rods(
an optional extra) , on a ratio of two pcs. for each base.
- (Optional)
Dowel Bar Supports( 8-10 pcs. per unit.)
INSTRUCTIONS.
- Mark the lines where the
D.U. Kit ®
should be placed, using a string
- Connect the bases to the
omega rails using the M-6 bolts and the fastening bolts.( The P.V.C.
liner should be pointing upwards.
- Position the constructive
D.U. Kit ®
on the substrate, under the tightened string..
- Fasten the bases to the
substrate by inserting the pegs into the holes.( In the case of concrete
substrate, use HILTI or similar bolts.)
- Assemble the Dowel bar
support units.
- Adjust the rails to the
desired heights (After adjustment the rails should be well tightened
using the fastening bolts)
- Insert the dowel bars
through the pre-punched holes and the support units (in a horizontal
direction)
- When the constructive
D.U. Kit
®
is properly set up, it
is possible to proceed with the casting!
|
 |