a ®

The prefabricated solution for leveling of fresh poured Concrete and the application of joints.

 
  a  
 

THE COMPONENTS

  1. Omega rail with P.V.C. liner, 4 meters in length, or according to the customer's specifications.
  2. 4 pc. of bases per each standard rail, or according to the customers specifications.
  3. 4 pc. of bolts M6+4 pc of nuts, on a ratio of one per base.
  4. 8-10 pc. of peg rods( an optional extra) , on a ratio of two pcs. for each base.
  5. (Optional) Dowel Bar Supports( 8-10 pcs. per unit.)

INSTRUCTIONS.

  1. Mark the lines where the D.U. Kit ® should be placed, using a string.
  2. Connect the bases to the omega rails using the M-6 bolts and the fasteners..( The P.V.C. liner should be pointing upwards.
  3. Position the constructive D.U. Kit ® on the substrate, under the tightened string
  4. Fasten the bases to the substrate by inserting the pegs through the holes.( In the case of concrete ,use HILTI or similar bolts.)
  5. Assemble the Dowel bar support units.
  6. Adjust the rails to the desired heights. (After adjustment the rails should be well tightened using the fastening bolts)
  7. Insert the dowel bars through the pre-punched holes and the support units (in a horizontal direction)
  8. When the constructive D.U. Kit ® is properly set up, and the reinforcing rods are in place, it is possible to proceed with the casting!